Work-package
[1] |
Workpackage
title |
Lead
contractor [2] |
Person-months
[3] |
Start
month [4] |
End-month
[5] |
Deliverable
[6] |
| 1 |
Identification of main issues |
1 |
28 |
0 |
2 |
|
| 2 |
Delocalisation, Globalisation and Europeanisation:
Concepts and trends |
1 |
19 |
3 |
23 |
1, 3 |
| 3 |
Impact of Europeanisation on the software industry |
4 |
50 |
3 |
23 |
1, 4 |
| 4 |
Impact of Europeanisation on the clothing industry |
2 |
12 |
3 |
23 |
1, 5 |
| 5 |
Impact of Europeanisation on the footwear industry |
3 |
17 |
3 |
23 |
1, 6 |
| 6 |
Impact of Europeanisation on the electronics industry |
5 |
17 |
3 |
23 |
1, 7 |
| 7 |
The role of governance structures and public policies |
6 |
13 |
3 |
23 |
1, 8 |
| 8 |
Successful Adjustment Strategies (Best Practice) |
5 |
17 |
3 |
23 |
1, 9 |
| 9 |
Social consequences of delocalisation |
4 |
47 |
3 |
23 |
1, 10 |
| 10 |
Primary and Secondary Data harmonisation |
3 |
159 |
10 |
16 |
2 |
| 11 |
Synthesis (final report) |
1 |
22 |
25 |
30 |
11 |
| 12 |
Dissemination |
4 |
6 |
29 |
29 |
12 |
| 13 |
Co-ordination |
1 |
12 |
0 |
30 |
|
| |
TOTAL |
|
419 |
|
|
|
| |
|
|
|
|
|
|
| [1] Workpackage number: WP 1 - WP n. |
| [2] Number of the contractor leading
the work in this workpackage. |
| [3] The total number of person-months
allocated to each workpackage. |
| [4] Relative start date for the work
in the specific workpackages, month 0 marking the start of the project,
and all other start dates being relative to this start date. |
| [5] Relative end date, month 0 marking
the start of the project, and all ends dates being relative to this
start date. |
| [6] Deliverable number: Number for
the deliverable(s)/result(s) mentioned in the workpackage: D1 -
Dn. |